Technical details:
Project size: | up to 50 MW |
Securing of land: | is largely completed |
Building application: | has been submitted to the authorities |
Environmental study: | is being drawn up |
Grant of construction permit is expected: | 09.2021 |
Currently planned start of the project construction phase: | 03.2022 |
Currently planned commissioning of the PV plant: | 12.2022 |
About the project
- up to max. 50 MW of power generation
- is located north of Marrakech
- The local municipalities have approved allocation of the planned PV plot area
- Initial talks have already been held with a mining company based there in the region about supplying the electricity generated by the PV plant in the future
- a grid connection point is envisaged about 2km away