
Technical details
Project size: | up to 55 MW |
Securing of land: | is largely completed |
Building application: | has been submitted to the authorities |
Environmental study: | is being prepared |
Grant of construction permit is expected: | 06.2022 |
Currently planned start of the project construction phase: | 06.2023 |
Currently planned commissioning of the Wind farm: | 06.2024 |
About the project
- up to max. 55 MW of power generation
- is located south of Casablanca
- the local municipalities have approved allocation of the planned wind turbine plot area
- a grid connection point is envisaged about 15 km away on a collective line for several wind farm projects in the region