Wind Farm North 01

Technical details:

Project size:up to 127 MW
Securing of land:is in testing
Building application:is being prepared
Environmental study:is being prepared
Grant of construction permit is expected:11.2022
Currently planned start of the project construction phase:09.2023
Currently planned commissioning of the Wind farm:12.2024

About the project

  • up to max. 127 MW of power generation
  • is located east of Tangier
  • the ministry responsible for the plot there has reviewed the allocation of the planned plots for the wind turbines.
  • a grid connection point is envisaged about 22 km away at our own substation in the region, to be constructed specially