Technical details:
Project size: | up to 127 MW |
Securing of land: | is in testing |
Building application: | is being prepared |
Environmental study: | is being prepared |
Grant of construction permit is expected: | 11.2022 |
Currently planned start of the project construction phase: | 09.2023 |
Currently planned commissioning of the Wind farm: | 12.2024 |
About the project
- up to max. 127 MW of power generation
- is located east of Tangier
- the ministry responsible for the plot there has reviewed the allocation of the planned plots for the wind turbines.
- a grid connection point is envisaged about 22 km away at our own substation in the region, to be constructed specially